§ 15.04.032. Electric vehicle charging stations.  


Latest version.
  • A.

    Purpose. The purpose of this section is to promote and encourage the use of electric vehicles by creating an expedited, streamlined permitting process for electric vehicle charging stations while promoting public health and safety and preventing specific adverse impacts in the installation and use of such charging stations. This section is also intended to comply with the requirements of California Government Code Section 65850.7, as it may be amended from time to time.

    B.

    Definitions.

    1.

    "Electric vehicle charging station" or "charging station" means any level of electric vehicle supply equipment station that is designed and built in compliance with Article 625 of the California Electrical Code, as it reads on the effective date of this Section, and delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle.

    2.

    "Specific, adverse impact" means a significant, quantifiable, direct, and unavoidable impact, based on objective, identified, and written public health or safety standards, policies, or conditions as they existed on the date the application was deemed complete.

    3.

    "Electronic submittal" means the utilization of one or more of the following:

    i.

    Electronic mail or email.

    ii.

    The internet.

    iii.

    Facsimile.

    C.

    Applicability. This section applies to the permitting of all electric vehicle charging stations in the city. Electric vehicle charging stations legally established or permitted prior to the effective date of this section are not subject to the requirements of this section unless physical modifications or alterations are undertaken that materially change the size, type, or components of a system in such a way as to require new permitting. Routine operations and maintenance or in-kind replacements shall not require a permit.

    D.

    Expedited Permitting Process. The building official shall implement an expedited, streamlined permitting process for electric vehicle charging stations, and adopt a checklist of all requirements with which electric vehicle charging stations shall comply with in order to be eligible for expedited review. The expedited, streamlined permitting process and checklist may refer to the recommendations contained in the most current version of the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" as published by the Governor's Office of Planning and research. The city's adopted checklist shall be published on the city's website.

    E.

    Permit Application Processing.

    1.

    Prior to submitting an application for processing, the applicant shall verify that the installation of an electric vehicle charging station will not have specific, adverse impact to public health and safety and building occupants. Verification by the applicant includes but is not limited to: electrical system capacity and loads; electrical system wiring, bonding and overcurrent protection; building infrastructure affected by charging station equipment and associated conduits, areas of charging station equipment and vehicle parking.

    2.

    A permit application that satisfies the information requirements in the city's adopted checklist shall be deemed complete and be properly processed. Upon confirmation by the building official that the permit application and supporting documents meets the requirements of the city adopted checklist, and is consistent with all applicable laws and health and safety standards, the building official shall, consistent with Government Code section 65850.7, approve the application and issue all necessary permits. If the building official determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.

    3.

    The building official shall allow for electronic submittal of permit applications covered by this section and associated supporting documentation. In accepting such permit applications, the building official shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by any applicant.

    F.

    Technical Review.

    1.

    It is the intent of this section to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the building official's authority to address higher priority life-safety situations. If the building official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in this section, the city may require the applicant to apply for an appropriate use permit as required by the Arroyo Grande Municipal Code.

    2.

    In the technical review of a charging station, the building official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080.

    G.

    Electric Vehicle Charging Station Installation.

    1.

    All electric vehicle charging stations shall meet applicable health and safety standards and requirements imposed by the state and the city. Electric vehicle charging station equipment shall meet all applicable safety and performance standards established by the California Electrical Code, the Institute of Electrical and Electronics Engineers, accredited testing laboratories such as the Underwriters Laboratories and, where applicable, rules of the public utilities commission regarding safety and reliability.

    2.

    Installation of electric vehicle charging stations and associated wiring, bonding, disconnecting means and overcurrent protective devices shall meet the requirements of Article 625 and all applicable provisions of the California Electrical Code.

    3.

    Installation of electric vehicle charging stations shall be incorporated into the load calculations of all new or existing electrical services and shall meet the requirements of the California Electrical Code. Electric vehicle charging equipment shall be considered a continuous load.

    4.

    Anchorage of either floor-mounted or wall-mounted electric vehicle charging stations shall meet the requirements of the California Building or Residential Code as applicable per occupancy, and the provisions of the manufacturer's installation instructions. Mounting of charging stations shall not adversely affect building elements.

    H.

    Decisions by the building official to deny a permit may be appealed to the planning commission as outlined in Section 16.12.150 of this code.

(Ord. No. 691, § 2, 3-27-2018)